glenn schrooyenandClaude Opus 5 37bac79ad8 SAFETY-04: clamp the integrator, not only the output
The loop was in velocity form: the accumulator WAS the commanded power, so
"clamp the integrator" and "clamp the output" were the same line of code and
could not be set apart. This makes the accumulator an explicit carried value
(`i_w`), bounds it with its own `integrator_max_w`, and keeps the output clamp
where it was. Killing either mechanism now still leaves the other holding -
which is the point of the ticket, and what the new regression test asserts.

Freeze semantics: while saturated the integrator may unwind but not wind
further. A strict freeze would strand the command at whatever it reached,
because the condition that releases it is the inverter tracking again, and not
tracking is exactly what saturation means.

The integrator is re-seeded from the arbiter's actual output whenever the loop
did not get what it asked for, so entering any failsafe (all of which resolve
to 0 W) zeroes it, and the first cycle after release does not dump the stale
period as power.

test_control.py: 24 -> 33 checks, all passing.

Co-Authored-By: Claude Opus 5 <noreply@anthropic.com>
Claude-Session: https://claude.ai/code/session_01Du77usMj8XNKNFZGmUiWDa
2026-08-24 21:44:05 +02:00

6.0 KiB
Raw Blame History

GoodWe RS485 Controller

Drives a GoodWe ES/BP battery inverter over its RS485 meter bus: holds net grid exchange at zero, and runs a monthly battery maintenance cycle so the BMS can balance cells and recalibrate its coulomb counter.

Installers: read FIELD-GUIDE.md in the repository. It is not optional reading — it contains the commissioning gates and the failure modes.

Before you start

You need:

  • A GoodWe ES / BP family inverter (AA55 / RS485 meter-bus generation)
  • The vendor's meter-emulating controller disconnected from the bus
  • A T-CAN485 (ESP32) flashed with firmware/goodwe-master.yaml
  • A grid-power sensor already working in Home Assistant, updating every ~510 s

The safety model, in short

The inverter holds its last command forever — it has no meter-timeout. So:

  • The ESP32 commands 0 W if this add-on stops refreshing for ~30 s, and keeps commanding it.
  • This add-on commands 0 W when its inputs go missing, when you stop control, and when it shuts down.
  • The optional RS485 e-stop is the only thing that covers this machine dying. Without it, a failed host leaves the battery latched at its last command until someone intervenes.

If anything looks wrong: stop the add-on. That commands 0 W and the hardware holds it there.

Configuration

Sources

option required meaning
meter_entity yes Net grid power. Positive must mean importing
meter_invert Flip the sign if the meter reports the other way
soc_entity yes Battery state of charge — use the ESP32's own read
batt_entity yes Battery power — again the ESP32's read, + = discharging
batt_invert Flip if needed
setpoint_entity yes The ESPHome number.*_goodwe_setpoint_w

Use the ESP32's readings rather than the inverter's cloud or dongle sensors: those serve cached values, and a stale reading here ends the maintenance charge phase having charged nothing.

Control

option default meaning
max_w 2000 Hard limit on what may be commanded. Start low, raise after commissioning
gain 0.6 Correction per cycle. At the limit — do not raise
slew_w 1000 Maximum change per cycle
deadband_w 15 Ignore errors smaller than this
target_grid_w -10 What the meter should rest at. Negative = a slight export
step_w 10 Quantisation
saturation_w 500 Divergence that counts as "the inverter is at a limit"
saturation_cycles 3 How many consecutive cycles before freezing. Do not set to 1
integrator_max_w 3000 Bound on the loop's accumulator, separate from max_w. Caps how much stale error can be waiting to unwind when the sign flips. Keep it above max_w, and do not set it equal to max_w
heartbeat_s 10 Refresh interval; must stay well under the firmware watchdog
stale_input_s 15 How long inputs may be missing before commanding 0 W
auto_start false Start controlling on boot (only after commissioning)

Why target_grid_w is not zero

The deadband is a one-way ratchet: any resting point inside it holds until something disturbs it. Import and export are separate registers on the meter, so a rest point of +14 W is billed for every second it holds and no amount of export cancels it - 14 W all day is 0.34 kWh.

Biasing the target below zero moves that residue into the export register, which is not billed. The resting band becomes target ± deadband, so:

target_grid_w resting band worst billed leak export given away
0 -15 … +15 W ~15 W (0.35 kWh/day) none
-10 -25 … +5 W ~5 W (0.12 kWh/day) ~10 W
-15 -30 … 0 W none ~15 W (0.36 kWh/day)

Set it to -deadband_w if injection is worth nothing to you and you would rather give the energy away than buy it back. Set it to 0 if you are paid properly for export, or if you are debugging and want the loop centred.

⚠️ This is a billing knob, not a speed knob. If import is arriving in bursts rather than as a trickle, the cause is tracking lag, and this will not help - see "Why the tuning is what it is".

Maintenance

option default meaning
maintenance_enabled false Enable the monthly cycle
maintenance_interval_days 28 Minimum gap between cycles
maintenance_start_hour 10 Hour of day a due cycle begins
maintenance_discharge_w 2500 Drain rate (exports the surplus)
maintenance_charge_w 2500 Charge ceiling, capped again by peak headroom
maintenance_soc_floor 11 Drain target — stay just above the inverter's own floor
maintenance_soc_target 99 Charge target
maintenance_hold_min 120 Hold at full so the BMS can balance

Tariff (all optional)

option meaning
peak_forecast_entity Quarter-hour demand forecast, for capacity-tariff markets. Empty = no cap
peak_cap_w The site's capacity-tariff target
price_now_entity, price_avg_entity Dynamic tariff. Empty = never force a paid grid top-up

On a capacity-tariff site the maintenance charge is capped by the headroom left under peak_cap_w, and if the forecast goes over the cap the charge-only clamp is dropped so the battery can shave the peak instead. Money outranks the maintenance schedule.

Site

option meaning
estop_fitted Whether the RS485 e-stop is installed. Drives the warning banner
log_level trace/debug/info/warning/error

The Web UI

The ingress panel shows live values, why the controller is commanding what it is, and a Commissioning checklist that names any problem in words. It also carries the three buttons: start/stop control, force a maintenance cycle, and abort one.

Status entities

If an MQTT broker is available the add-on publishes setpoint, grid power, battery power, state of charge, maintenance phase and controller status by MQTT discovery. This is observability only — the controller works fine without a broker, and MQTT problems can never affect control.