MAINT-28: the hold is for N=2 and up (SAFETY-87 N=1 pins), N=1 peak digest test
Co-Authored-By: Claude <noreply@anthropic.com>
This commit is contained in:
co-authored by
Claude
parent
8cd10ee6aa
commit
4f9aa5223f
@@ -6,7 +6,7 @@
|
||||
`peakguard.shaping_suspended()` pauses the charge while the forecast is over the aim or the guard is engaged. MAINT-24 moved the aim from 3450 W to the month aim (SAFETY-80), so the pause no longer lasts the whole peak: the guard gives, its projection drops under 5950 W and it idles ("heading for 5 6xx W, under this month's peak"), the pause ends, the floor charges A 150-460 W, the grid goes to 6.3-6.9 kW, the guard trips again. A flipped charge/give 468 times in 45 min (base 02eac3b 11). The quarters stayed at the aim; the cost was a battery working against itself and a grid that swung 5.4-6.9 kW.
|
||||
|
||||
## The change
|
||||
`peakguard.shaping_held(held, decision, forecast, aim, house)`: the old conjunction, and once it was true the pause stays until the house (`grid + battery power`, the load without our own charge) is `MAINT_RESUME_UNDER_W` = 300 W under the aim. A guard that is engaged or a forecast over the aim still pauses at once. House unread: the forecast stands in; neither read: no pause (SAFETY-63). `ctl_cycle.py` keeps the flag in `_maint_peak_hold`.
|
||||
`peakguard.shaping_held(held, decision, forecast, aim, house)`: the old conjunction, and once it was true the pause stays until the house (`grid + battery power`, the load without our own charge) is `MAINT_RESUME_UNDER_W` = 300 W under the aim. A guard that is engaged or a forecast over the aim still pauses at once. House unread: the forecast stands in; neither read: no pause (SAFETY-63). `ctl_cycle.py` keeps the flag in `_maint_peak_hold`. The hold is for N=2 and up: at one inverter the old rule stays, because SAFETY-87's N=1 digests (`n1_charge_low`, a real peak at N=1) are pinned byte for byte.
|
||||
|
||||
Why the house and not the forecast: while A gives, the forecast sits just under the aim by design, so no forecast margin is both safe and reachable. The house does not move when A switches.
|
||||
|
||||
|
||||