Validator refusals name the setting by its label and key, say what is
wrong and what to change, and keep the rejected value and limit. Option
names and descriptions are short in en and nl; citations moved to DOCS
"For installers" and the test_translations citation check now pins the
instruction on the tab and the record in DOCS. No rule, key, schema,
default or exit code changed. Allowlist 167 -> 43 (log lines only).

Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
Claude-Session: https://claude.ai/code/session_01LyR88rXETvwhTgx6yHE39p
This commit is contained in:
glenn schrooyen
2026-09-27 05:55:45 +02:00
co-authored by Claude Opus 5.5
parent e1d0970b23
commit 2c516a032c
26 changed files with 1026 additions and 1236 deletions
+143 -1
View File
@@ -125,7 +125,7 @@ whole rendered list, in both languages.
| **Order comes from `schema:`** | `App.schema_ui` is `UiOptions(...)(data["schema"])`, so the **schema half** of `config.yaml` decides the order the tab renders in — not the `options:` half |
| **There are no section headers** | Add-on options are a flat list: no header primitive, no per-option advanced flag, no units on the input, no sliders. Grouping is approximated by **order** plus the `Group · ` prefix in each label, and by nothing else |
| **Groups, in task order** | Hardware → Meter → Limits → Tariff → Maintenance → Safety → Advanced |
| **The description says whether to touch it** | A number that was **derived** names the campaign it came from and says not to change it without re-deriving; a number that is genuinely yours (`max_w`, `peak_cap_w`) says **"THIS IS YOUR NUMBER"**; and `cycle_cost_threshold_eur`, which is neither, says it is an open product question |
| **The description says whether to touch it** | One or two plain sentences. A measured or derived value says "leave it unchanged", a number that is genuinely yours (`max_w`, `peak_cap_w`) says "Your own number", and `cycle_cost_threshold_eur` says it is a product choice. Where each number comes from is under [For installers](#for-installers-where-the-numbers-come-from) |
| **Dutch falls back per key** | `translations[your language]?.name \|\| translations["en"]?.name \|\| the raw key`. A key missing from `nl.yaml` degrades to English; a key present but wrong does not degrade at all |
| **⚠️ The per-entry keys inside `inverters:` still render raw** | Measured, and negative. A list-of-objects becomes an `object` selector with `multiple: true`, and `ha-selector-object` labels its fields `fields[name].label \|\| name` — the converter sets no `label` and no `translation_key`. The `fields:` translations are shipped and validated (they are the shape Supervisor's own schema defines) but on frontend 20250925.1 they do **not** reach the screen. The `inverters` label and description themselves do |
@@ -133,6 +133,148 @@ whole rendered list, in both languages.
option that does not exist, or an option with no translation, fails CI — in
either direction, and the check is mutation-tested both ways.
### Settings at a glance
The label and description each setting shows on the Configuration tab, in tab order. `translations/en.yaml` is the source, and `test_translations.py` keeps this table in step with it.
| Group | Setting | Key | What it does |
|---|---|---|---|
| Hardware | Inverter setpoint entity | `setpoint_entity` | The ESPHome number entity the add-on writes the inverter's power to. Leave it empty when you fill in the inverter list. |
| Hardware | Battery level entity (%) | `soc_entity` | The sensor with the battery level in percent. Use the control board's own reading. |
| Hardware | Battery power entity (W) | `batt_entity` | The sensor with this inverter's battery power. Positive must mean the battery is giving power. |
| Hardware | Battery power sign is reversed | `batt_invert` | Switch this on only if your battery power sensor shows giving power as a negative number. |
| Hardware | Inverter list | `inverters` | Leave it empty if you have one inverter. With two or more, add one entry per inverter, which replaces the inverter settings above. |
| Hardware · Inverter list | Name | `inverters.name` | A short, unique name for this inverter, for example inverter-a. |
| Hardware · Inverter list | Setpoint entity | `inverters.setpoint_entity` | This inverter's own ESPHome setpoint entity. Two entries may not use the same one. |
| Hardware · Inverter list | Inverter rating (W) | `inverters.max_w` | The most power the add-on may ask of this inverter. The site total is the sum of the list. |
| Hardware · Inverter list | Battery cut-out level (%) | `inverters.bms_soc_floor` | The level at which this battery's own management system stops giving power. Read it off the battery that is installed. |
| Hardware · Inverter list | Battery level entity (%) (optional) | `inverters.soc_entity` | This battery's own level sensor. Leave it empty if this inverter has none. |
| Hardware · Inverter list | Battery power entity (W) (optional) | `inverters.batt_entity` | This inverter's own battery power sensor. Leave it empty if it has none. |
| Hardware · Inverter list | Battery power sign is reversed (optional) | `inverters.batt_invert` | Switch this on if this inverter's sensor shows giving power as a negative number. |
| Hardware · Inverter list | Usable battery capacity (kWh) (optional) | `inverters.capacity_kwh` | This battery's usable capacity from its datasheet. Fill it in on every inverter or on none, and the work is then shared by energy left. |
| Hardware | RS485 emergency stop is fitted | `estop_fitted` | Switch this on if the emergency stop is installed. It only changes a warning on the status page. |
| Hardware | Solar production entity (W) | `pv_entity` | Optional. Your solar inverter's power sensor, positive while producing. The add-on records it and does not use it for control. |
| Hardware | Solar production entities, per inverter (W) | `pv_entities` | Optional. Use one row per solar inverter instead of “Solar production entity” when you have several. If one stops reporting, no total is recorded. |
| Hardware | Reversed-sign solar entities | `pv_invert_entities` | Optional. Add each solar entity above that reads negative while producing, spelled the same way. Its sign is flipped before adding up. |
| Meter | Where the meter reading comes from | `meter_source` | How the add-on reads your meter. 'off' uses “Grid power entity” below, and only homewizard_local can spot a stuck meter. |
| Meter | Grid power entity (W) | `meter_entity` | Used when the meter source is 'off'. Positive must mean drawing from the grid. |
| Meter | Grid power sign is reversed | `meter_invert` | Switch this on if your grid sensor shows drawing from the grid as a negative number. |
| Meter | Number of phases (1 or 3) | `meter_phases` | Must match your grid connection. Meter readings with a different number of phases are rejected. |
| Meter | HomeWizard P1 address | `p1_host` | For homewizard_local only. The meter's address on your network, as host or host:port. |
| Meter | Time between meter reads (s) | `meter_poll_s` | For homewizard_local only. The meter updates every 5 s, so lower gains nothing. Keep it well below “Reading too old after”. |
| Meter | Reading too old after (s) | `meter_max_age_s` | After this a meter reading counts as missing. The “Missing inputs time limit” starts only after this one runs out. |
| Meter | MQTT topic | `meter_mqtt_topic` | For mqtt_p1 only. The topic your meter readings are published on. |
| Meter | Grid import entity (W) | `p1_import_entity` | The sensor for power drawn from the grid, never negative. The add-on works out the net value itself. |
| Meter | Grid export entity (W) | `p1_export_entity` | The sensor for power fed into the grid, never negative. It pairs with “Grid import entity”. |
| Meter | Signed net power entity (W) | `p1_net_entity` | For ha_signed only. One sensor that is positive when drawing from the grid and negative when feeding in. |
| Meter | Import entities per phase (L1-L3) | `p1_phase_import_entities` | Optional, in L1, L2, L3 order. Needed for the peak limit on a three-phase connection, one entry per phase. |
| Meter | Export entities per phase (L1-L3) | `p1_phase_export_entities` | Optional, in L1, L2, L3 order, next to the import entities per phase. One entry per phase. |
| Meter | Net entities per phase (L1-L3) | `p1_phase_net_entities` | For ha_signed only. Optional, in L1, L2, L3 order, signed like “Signed net power entity”, one entry per phase. |
| Limits | Inverter rating (W) | `max_w` | Your own number: the most power the add-on may ever ask of the inverter. Start low and raise it after commissioning. |
| Limits | Battery cut-out level (%) | `bms_soc_floor` | The level where the battery's own management system stops giving power. Read it off your battery rather than copying a figure. |
| Limits | Peak limit (W) | `peak_cap_w` | Your own number: the 15-minute average power the add-on keeps the grid under. Take it from your grid contract. |
| Limits | 15-minute demand forecast entity (W) | `peak_forecast_entity` | Optional. A forecast of this 15-minute period's average power. Leave it empty and there is no peak limit. |
| Limits | Peak reserve (%) | `peak_soc_floor` | Peak limiting will not draw the battery below this level, but ordinary use can. Derived value, leave it unchanged. |
| Tariff | Dynamic price source | `price_provider` | Where prices come from. Choosing a source starts the price fetch, even with trading off. |
| Tariff | Supplier markup (EUR/kWh) | `price_markup_eur_kwh` | Your supplier's margin. It is added only when the price source does not already include it. |
| Tariff | Distribution, levies and VAT (EUR/kWh) | `price_taxes_eur_kwh` | Grid costs, levies and VAT per kWh, preset for Flanders. Check it against your own grid operator's rates. |
| Tariff | Injection price (EUR/kWh) | `export_price_eur_kwh` | What you are paid per kWh fed into the grid, all in. It may be negative. |
| Tariff | Fixed or day/night tariff (JSON) | `static_profile` | Your fixed or day/night contract as one line of JSON, prices all in. Fill it in even on a dynamic contract, as the fallback when the price feed fails. |
| Tariff | Day/night levies and VAT (JSON) | `price_taxes_profile` | Leave it empty unless your grid operator charges a different day and night rate, as in Wallonia and Brussels. Set this or the flat figure above, not both. |
| Tariff | Your own tariff formula (JSON) | `price_formula` | For custom_formula only. Type the numbers from your supplier's tariff card as one line of JSON, and the add-on checks them against the card. |
| Tariff | Your own injection formula (JSON) | `price_export_formula` | Optional. The injection formula from your tariff card, in the same shape as your own tariff formula. Leave it empty to use the flat injection price. |
| Tariff | Price CSV file | `price_csv_path` | For manual_csv only. Where in /share the add-on reads your price file. |
| Tariff | Price feed URL override | `price_feed_url` | Leave it empty to use the source's own feed. An override is sent exactly as typed and often returns only one day. |
| Tariff | Price look-ahead (hours) | `price_horizon_h` | How many hours of prices to ask the source for. |
| Tariff | Price request timeout (s) | `price_timeout_s` | How long one request to the price source may take before it is given up. |
| Tariff | Current price entity (older) | `price_now_entity` | The older way to get a price, used only to charge in a cheap window during maintenance. Do not combine it with a dynamic price source. |
| Tariff | Average price entity (older) | `price_avg_entity` | The average the current price is compared with. Use it only with the current price entity, not with a dynamic price source. |
| Tariff | Trade on the price spread | `arbitrage_enabled` | Charge in the cheapest hour and draw the battery down in the dearest, when the spread covers the cost. Turning it off does not turn the price feed off. |
| Tariff | Battery cycle cost (EUR/kWh) | `cycle_cost_threshold_eur` | What one full battery cycle costs per kWh. A smaller price spread is not traded, and the value is a product choice, not a measured one. |
| Tariff | Trading keeps at least (%) | `arbitrage_soc_floor` | Price trading will not draw the battery below this level. It is separate from the maintenance settings. |
| Tariff | Trading charges at most (%) | `arbitrage_soc_ceiling` | Price trading will not charge the battery above this level. |
| Maintenance | Run the monthly battery cycle | `maintenance_enabled` | Once a month, empty the battery deeply, charge it full and hold it there, so its level reading stays accurate. Off by default. |
| Maintenance | Minimum days between cycles | `maintenance_interval_days` | The shortest gap between two maintenance cycles. |
| Maintenance | Start hour | `maintenance_start_hour` | The local hour, 0 to 23, at which a due cycle starts. |
| Maintenance | Draw-down rate (W) | `maintenance_discharge_w` | How fast the cycle empties the battery. Above “Inverter rating” it is cut back to the rating, and the cycle just takes longer. |
| Maintenance | Recharge rate (W) | `maintenance_charge_w` | How fast the cycle recharges the battery. It must be at or below “Inverter rating”, or the add-on will not start. |
| Maintenance | Draw down to (%) | `maintenance_soc_floor` | The level the monthly cycle empties the battery to. It is not the “Peak reserve”, and the two differ on purpose. |
| Maintenance | Recharge up to (%) | `maintenance_soc_target` | The level the recharge aims for before the hold starts. |
| Maintenance | Hold at full for (minutes) | `maintenance_hold_min` | How long the battery stays full so its cells can balance. |
| Safety | Wrong-direction threshold (W) | `sign_disagree_w` | A wrong direction counts only when the command and the meter reading both exceed this. Measured value, leave it unchanged. |
| Safety | Wrong-direction time (s) | `sign_disagree_s` | How long a wrong direction may last before a safety stop sets every inverter to 0 W. Measured value, leave it unchanged. |
| Safety | Per-inverter wrong-direction threshold (W) | `unit_sign_disagree_w` | For two or more inverters: the wrong-direction threshold for each inverter. Derived value, leave it unchanged. |
| Safety | Per-inverter wrong-direction time (s) | `unit_sign_disagree_s` | For two or more inverters: how long one inverter may push the wrong way before it is set to 0 W. Derived value, leave it unchanged. |
| Safety | Site wrong-direction threshold (W) | `site_sign_disagree_w` | For two or more inverters: the wrong-direction threshold for the whole site. Measured value, leave it unchanged. |
| Safety | Site wrong-direction time (s) | `site_sign_disagree_s` | For two or more inverters: how long the whole site may push the wrong way before a safety stop. Derived value, leave it unchanged. |
| Safety | Stuck meter alarm after (s) | `meter_freeze_s` | An alarm when the meter repeats one reading this long while the command is at full power, with homewizard_local only. Measured value, leave it unchanged. |
| Safety | Opposing inverters threshold (W) | `circulation_w` | For two or more inverters: how much power one may push against another before it counts. Measured value, leave it unchanged. |
| Safety | Opposing inverters time (s) | `circulation_hold_s` | For two or more inverters: how long they may push against each other before a safety stop. Derived value, leave it unchanged. |
| Safety | Not delivering alarm after (s) | `delivery_hold_s` | For two or more inverters: how long one may fall short of its share before an alarm, which changes nothing. Derived value, leave it unchanged. |
| Safety | Shadow mode | `shadow_mode` | The add-on makes every decision but keeps every inverter at 0 W. 'auto' does this while control is stopped, 'on' always, 'off' never. |
| Advanced | Start control on boot | `auto_start` | Off by default. Leave it off until the site is commissioned, so someone presses Start after each restart. |
| Advanced | Control gain | `gain` | How much of the remaining error control corrects each cycle. Measured on real hardware, do not raise it. |
| Advanced | Largest change per cycle (W) | `slew_w` | How far the command may move in one cycle. 0 follows “Inverter rating” and is recommended. |
| Advanced | Ignore errors below (W) | `deadband_w` | Errors smaller than this are ignored. Keep it small, since any resting point inside it holds. |
| Advanced | Meter resting point (W) | `target_grid_w` | What the meter should show when nothing happens. A slight export avoids paying for tiny imports all day. |
| Advanced | Command rounding (W) | `step_w` | The command is rounded to a multiple of this, so noise does not change it every cycle. |
| Advanced | Inverter at limit gap (W) | `saturation_w` | When an inverter delivers this much less than asked, it counts as at its limit. The per-inverter wrong-direction threshold is half of this. |
| Advanced | Cycles at limit before freezing | `saturation_cycles` | How many cycles in a row at the limit before control stops building up error. Do not set it to 1. |
| Advanced | Error build-up limit (W) | `integrator_max_w` | Limits how much old error control can carry, and 0 means “Inverter rating”. Do not raise it above the rating. |
| Advanced | Command refresh interval (s) | `heartbeat_s` | How often the command is sent again even when unchanged. Keep it well under the control board's own 30 s limit. |
| Advanced | Missing inputs time limit (s) | `stale_input_s` | How long inputs may be missing before every inverter is set to 0 W. With a P1 meter it starts after “Reading too old after”. |
| Advanced | Longest time between cycles (s) | `cycle_floor_s` | A deadline between control cycles that a healthy meter never reaches. Raise it only for a meter slower than about 10 s. |
| Advanced | Log level | `log_level` | How much detail the add-on writes to its log. 'debug' and 'trace' are for finding a problem. |
### For installers: where the numbers come from
The Configuration tab keeps each description to one or two sentences. The detail that used to sit there is here, one entry per setting. A value marked *measured* or *derived* in its description came from the record named below; change it only after re-deriving it from a new measurement.
When the add-on refuses to start, each reason names the setting by its label and then its key, for example “Inverter rating” (max_w), and adds the inverter's name when there is a list. The configuration panel shows a reason beside every setting it names.
- **Battery power entity** (`batt_entity`): on the reference installation this is holding register 0x0518, read by the control board. The wrong-direction checks and the opposing-inverters alarm both grade each inverter against it.
- **Inverter list** (`inverters`): empty means the single-inverter settings describe the one inverter you have. Filled in, the list replaces them and nothing is inherited: each entry names its own setpoint entity, rating and cut-out level, so no inverter is judged by another's numbers. “Inverter setpoint entity” must then be empty, and the add-on refuses to start when both are set. Each entry's name keys its own safety stop and records in the add-on's state, so two entries may not share one.
- **Usable battery capacity** (`inverters.capacity_kwh`): read only to share the site target by the energy each battery has left rather than by its rating. The reference batteries are 5000 W with 15.36 kWh and 4600 W with 20.48 kWh, so the two ways of sharing give the work to different batteries. Stated on some entries and not others, the add-on refuses to start.
- **Solar production entities** (`pv_entity`, `pv_entities`, `pv_invert_entities`): measurement only, no control behaviour changes. The unit is read off each entity, so a sensor without one is refused rather than guessed. With several entities, one that stops reporting gives no site total at all, because a partial sum looks like a real one. Setting `pv_entities` ignores `pv_entity`.
- **Where the meter reading comes from** (`meter_source`): 'off' keeps “Grid power entity”. ha_dsmr follows the DSMR integration, mqtt_p1 reads an MQTT topic, ha_signed reads one signed entity (what a HomeWizard P1 publishes), and homewizard_local polls the meter's own local API. Only homewizard_local can tell "the meter did not answer" from "the value did not change", so the stuck-meter alarm only means something there.
- **Grid import and export entities** (`p1_import_entity`, `p1_export_entity`, `p1_net_entity`): the add-on computes net power itself, so the sign convention lives in tested code rather than in a template sensor.
- **Number of phases** (`meter_phases`): a reading whose phase count disagrees is rejected and logged as it arrives, so a wrong value shows up at once. The range accepts 2, which is not a real Belgian connection.
- **Time between meter reads, Reading too old after** (`meter_poll_s`, `meter_max_age_s`): the add-on refuses to start if the poll interval is at or above the age limit. 30 s is six polls of headroom at the default 5 s. The reading-age limit on its own does not command 0 W. “Missing inputs time limit” starts after it, so the two add up.
- **Inverter rating** (`max_w`): your own number, not a derived one. It is not read when the inverter list is filled in, since each entry carries its own and the site limit is their sum. Several safety thresholds must stay below it, and the add-on refuses to start if one does not.
- **Battery cut-out level** (`bms_soc_floor`, `inverters.bms_soc_floor`): measured, not chosen. Register 0x0560 reads 10 % on the reference GW5000S-BP. It exists so the add-on can refuse a “Peak reserve” at or below it, which could never take effect. Each inverter entry states its own, because one default for two different batteries protects the shallower one with the deeper one's number.
- **Peak limit** (`peak_cap_w`): your own number, from your grid contract. In Belgium it is the capacity-tariff peak your distribution charge is billed on.
- **Peak reserve** (`peak_soc_floor`): derived, not picked (SAFETY-24). The reference battery holds 13.8 kWh usable and the worst modelled peak day asks for 878 Wh, or 6.4 %. 20 % sits ten points above the cut-out level and leaves about 1.6 worst days of room. It bounds peak limiting only: ordinary use goes on down to the cut-out level. It must stay above “Battery cut-out level”.
- **Dynamic price source** (`price_provider`): selecting a provider is what starts the fetch, every half hour, whether or not trading is on. It may not be combined with the two older price entities. engie_dynamic, totalenergies_dynamic and eneco_eddy are withdrawn and refuse to start: their endpoints never existed. They stay in the list only so such a site gets that explanation.
- **Supplier markup** (`price_markup_eur_kwh`): under manual_csv, whose prices are all in, it is ignored and logged as ignored.
- **Distribution, levies and VAT** (`price_taxes_eur_kwh`): 0.11736 EUR/kWh, derived in TARIFF-18 from the Eneco residential card for Flanders of September 2026 with 6 % VAT: Fluvius distribution for Antwerpen 5,35 plus excise 4,876 plus green power and CHP levy 1,51 c/kWh. Check it against your own DSO: across the eight Fluvius areas distribution runs from 5,28 to 6,70 c/kWh, so the Flemish total runs from about 0.117 to 0.131. Changing it moves no trading decision, because the same amount lands on every hour. It does move every price shown, and the rule that refuses to draw the battery down into an hour priced below zero. See [What `price_taxes_eur_kwh` is made of](#what-price_taxes_eur_kwh-is-made-of-and-why-yours-is-different-tariff-18).
- **Day/night levies and VAT** (`price_taxes_profile`): for Wallonia and Brussels, where distribution has a day and a night rate (ORES 13,27 against 7,39 c/kWh, AIESH 15,17 against 8,21, Sibelga 9,39 against 7,10). The figures are levies alone, added to the market price. The add-on refuses to start if it and the flat figure disagree. See [Levies and VAT by time of day](#levies-and-vat-by-time-of-day-price_taxes_profile).
- **Injection price** (`export_price_eur_kwh`): one number because no supplier here publishes a dynamic injection curve. In Belgium it is often near zero, and at a sunny midday it can be negative.
- **Fixed or day/night tariff** (`static_profile`): the periods must cover every day type exactly once with no gap and no overlap, and a gap is refused rather than filled. A window 22:00-07:00 on mon-fri does not cover Saturday morning, so a weekend row is required. See [Static day/night and fully-fixed tariffs](#static-daynight-and-fully-fixed-tariffs-static_profile).
- **Your own tariff and injection formula** (`price_formula`, `price_export_formula`): type the card's numbers in the card's units. The `card` block is required on the tariff formula: the add-on recomputes the card's example price and refuses to start if it does not come out. Injection is VAT-exempt in Belgium, so `vat_pct` there is normally 0. See [Your own tariff formula](#your-own-tariff-formula-custom_formula) and [`price_export_formula`, field by field](#price_export_formula-field-by-field).
- **Price feed URL override** (`price_feed_url`): only a host the chosen source declares is accepted. Nothing is added to the URL, not even the date range, so an override often returns one day and the rest of the plan is carried over and excluded from trading. The log warns on every refresh.
- **Current and average price entities** (`price_now_entity`, `price_avg_entity`): kept because removing them would take the maintenance cycle's only price signal away from a live site.
- **Trade on the price spread** (`arbitrage_enabled`): off as shipped, on purpose, because it moves energy against the meter by design. It needs a price source and a P1 meter, and the add-on refuses combinations that cannot work.
- **Battery cycle cost** (`cycle_cost_threshold_eur`): wear plus conversion losses. It is not derived from a measurement: 0.10 is a product decision still open with the owner (OPT-08). At this value a fixed day/night site does not trade, since a realistic Belgian day/night spread is about 0.08 EUR/kWh.
- **Trading keeps at least, Trading charges at most** (`arbitrage_soc_floor`, `arbitrage_soc_ceiling`): kept apart from the maintenance levels, so one setting does not couple two unrelated policies.
- **Draw-down and recharge rate** (`maintenance_discharge_w`, `maintenance_charge_w`): the draw-down rate above the rating is cut back, not refused. A recharge rate above the rating would ask for more than the limit allows and resolve to 0 W, so maintenance would never charge. That is why the add-on refuses it.
- **Draw down to** (`maintenance_soc_floor`): the monthly cycle goes this deep on purpose, while “Peak reserve” is a depth peak limiting never reaches. 11 % against 20 % is why they are two settings.
- **Wrong-direction threshold and time** (`sign_disagree_w`, `sign_disagree_s`): measured, not chosen (SAFETY-02). On the captured healthy day (2026-08-23) signs agree on 93.4 % of gated samples, on the fault day (2026-08-20) 0.0-10.5 %, with opposed runs up to 1752 s. The longest legitimate opposed run is 30 s, and the fault day still trips 13 times at 300 s, so 180 s sits in a wide gap. The threshold must stay below “Inverter rating”.
- **Per-inverter wrong-direction threshold and time** (`unit_sign_disagree_w`, `unit_sign_disagree_s`): two or more inverters only. Derived from 1890 closed-loop test runs (SAFETY-30) with nothing faulty. 250 W is half the at-limit gap. 85 s is 8.5 times the worst legitimate opposition (10.0 s) and 2.8 times the control board's 30 s link limit.
- **Site wrong-direction threshold** (`site_sign_disagree_w`): the single-inverter 300 W carried across deliberately (SAFETY-30), because near zero the sign is noise whatever is behind the one meter.
- **Site wrong-direction time** (`site_sign_disagree_s`): derived from the same 1890 runs (SAFETY-30). The worst legitimate opposition at 300 W is 110 s with one inverter and 215 s with two, so 180 s would false-trip. 325 s is 1.51 times that and inside the 900 s billing period.
- **Stuck meter alarm after** (`meter_freeze_s`): measured, not chosen (SAFETY-18). Over 2399 s of this house at its operating point, the longest run without a new reading is 15.4 s, and 300 s is 19.5 times that. It raises an alarm only and does not set 0 W.
- **Opposing inverters threshold** (`circulation_w`): measured on 924 closed-loop test runs (SAFETY-31). The worst legitimate opposition drops from 505 s at 100 W to 5 s at 400 W, the lowest value accepted. 700 W is 1.75 times that knee, with margin because the second inverter is still a copy of the first.
- **Opposing inverters time** (`circulation_hold_s`): derived (SAFETY-31). 75 s is fifteen control cycles, 15 times the worst legitimate episode, and 2.5 times the control board's 30 s link limit.
- **Not delivering alarm after** (`delivery_hold_s`): two or more inverters only. It reports only (SAFETY-42): nothing is commanded differently. Derived from 2640 closed-loop test runs with nothing faulty. The worst legitimate episode is 35.0 s and 185 s is 5.29 times that. The schema allows 30 s, below that, so expect false reports there. A battery at or below its own cut-out level is never reported. Re-derive with admin/goodwe `sim/delivery_window.py --campaign --blag`.
- **Shadow mode** (`shadow_mode`): the whole decision path runs and nothing reaches the inverter. The status page and action log show what would have been sent. A safety stop that is already up stays up. See [Shadow mode](#shadow-mode-shadow_mode-safety-10).
- **Control gain** (`gain`): measured on real hardware and already at the limit.
- **Largest change per cycle** (`slew_w`): 0 means follow the rating: about a ninth of it, derived (SAFETY-39) from a measured ~18 s step response against a 2 s meter tick. A fixed value faster than the rating allows is refused. At 1000 W against a 5000 W rating control swung the meter from 3.4 kW export to 2.8 kW import on 2026-09-05.
- **Ignore errors below, Meter resting point** (`deadband_w`, `target_grid_w`): the meter's import counter bills every positive watt, so a resting point at 0 W leaks about half the deadband as billed import, roughly 0.2-0.35 kWh a day at 15 W. -10 W moves that leak to export.
- **Inverter at limit gap** (`saturation_w`): the per-inverter wrong-direction threshold is derived as half of it, so moving this moves that argument too.
- **Error build-up limit** (`integrator_max_w`): measured on the closed-loop simulator with a 4000 W load dropped to zero: at a limit equal to the rating the command is 1000 W two cycles later, at 1.5 times the rating 1800 W. Lowering it is the useful direction.
- **Command refresh interval** (`heartbeat_s`): the control board refuses a link that has been quiet for 30 s.
- **Longest time between cycles** (`cycle_floor_s`): keep it under “Reading too old after”, since past that there is no reading left to act on.
### Sources
| option | required | meaning |